Getting a building plan sanctioned by MCD
In Delhi, the size of your plot, and whether it needs NOCs or faces a notified road, decides whether anyone at MCD looks at your drawings before you build. On a fresh residential plot of up to 500 sq m, under 15 m tall and with neither, the permit is released through MCD’s online system by the professional you hire.
The rules below are from the Unified Building Bye-Laws for Delhi 2016 (UBBL) and MCD’s Ease of Doing Business pages. DDA’s guidelines name the other authorities.
Check that the plot is MCD’s
MCD is one of several building authorities in Delhi. DDA’s guidelines under the bye-laws also name the New Delhi Municipal Council, DDA itself and the Delhi Cantonment Board, each for its own area. MCD’s process also assumes the plot is part of an approved layout plan, which its page says the town planning department holds. The bye-laws leave plots in the Lutyens’ Bungalow Zone out of the simplified schemes below (2.0.1 and Table 3.1).
Who signs off, by plot size
For a fresh residential building, MCD’s Citizen Corner sets out the sanctioning authority like this:
| Residential plot | Risk category | Who releases the sanction |
|---|---|---|
| Up to 105 sq m (SARAL scheme) | Very low | Architect, engineer or supervisor |
| 105 to 200 sq m | Low | Architect, engineer or supervisor |
| 200 to 500 sq m | Low | Architect or engineer |
| Above 500 sq m | Moderate | MCD Building Department |
| Any size, if NOCs are needed or the plot is on a notified road | MCD Building Department |
The same page lists who may prepare a plan at all. An architect can do it for a plot of any size, an engineer up to 500 sq m and a supervisor up to 200 sq m. Additions, alterations, revised plans and revalidation of an existing permit all go to the Building Department, as does every non-residential building.
The page is not fully consistent with itself. Its flowchart links label low risk as 105 to 200 sq m, while the low-risk flowchart and the bye-laws (Table 3.1) both say 105 to 500 sq m. The bye-laws also cap low and very low risk at a height below 15 m including stilt.
What a professional’s sanction means
For low-risk plots, UBBL bye-law 3.1.1.2 lets an architect or engineer issue the building permit themselves, “but only after submitting the plan along with requisite documents and fees to the Sanctioning Authority.” The owner can still ask MCD to sanction the plan itself, in which case the bye-law gives MCD 10 days. MCD’s table also lets a supervisor release the permit for 105 to 200 sq m, though the bye-law names only architects and engineers.
On plots up to 105 sq m, Chapter 4 of the bye-laws goes further than MCD’s table, which still has a professional release the permit. The owner files an undertaking called “Intimation of Construction Start” with the fee and can start immediately. No scrutiny happens at submission. The owner indemnifies the authority for structural safety, finishes within five years, and on completion files an “Intimation of Completion” with drawings signed by the architect or engineer before moving in.
MCD’s checks come later, at the plinth and at completion, and bye-law 2.5.1.1 puts responsibility for any deviation in between on the professional and the owner.
The steps on NexGen OBPS
MCD’s online system is NexGen OBPS. MCD’s flowcharts for a residential plot run like this:
- The owner registers, uploading ownership documents and identity proof.
- The owner picks an empanelled professional on the portal, and can change them later.
- The professional prepares the Common Application Form with the AutoCAD drawings, proof of ownership, an e-undertaking and a structural stability certificate.
- The system runs a “self confirmatory test” of the drawings against the rules.
- The fee is paid and the sanction is released. Where NOCs are needed, the file first goes to the Building Department and the NOC agencies, and can be sent back for corrections.
- Work starts. At plinth level, the professional inspects and files the report on Form C-2 for very low and low-risk buildings. For moderate and high-risk buildings the owner reports plinth completion on Form C-1 and MCD inspects. No work above plinth is allowed until the report is in (bye-law 2.5.5).
- On completion, the owner applies for the occupancy-cum-completion certificate along with the NOCs it needs, such as fire and water, and the departments carry out a single joint inspection.
Deadlines in the bye-laws
| Stage | Limit in UBBL 2016 |
|---|---|
| Sanction, moderate-risk building | 20 days (3.1.0) |
| Sanction, high-risk building | 30 days (3.1.0) |
| Sanction by MCD on request, low-risk plot | 10 days (3.1.1.2) |
| NOC from an outside agency | 15 days, else deemed issued (2.3.3) |
| Owner’s reply to shortcomings | 15 days, else rejected and fee forfeited (2.3.5) |
| Validity of the permit | 5 years, with work starting within 1 year (2.4.1) |
If MCD misses its limit, the plan is deemed sanctioned, but it is released only after the owner confirms the fees are paid (2.3.4(a)), and a deemed sanction still does not authorise anything against the lease, the master plan or the bye-laws (2.3.4(b)). Each time MCD raises a shortcoming, the clock restarts from your last reply (2.3.6). An application for the completion certificate is not entertained more than 30 days after the permit expires (2.4.3). MCD’s page gives no figures for how long sanctions take in practice.
Documents to keep ready
Bye-law 2.1 asks for these with the application:
- site plan, building plans and service plans
- a layout plan for plots of one hectare or more, and a planting and open-space plan where the Delhi Urban Art Commission’s approval is needed
- ownership proof such as the sale, lease or conveyance deed, and for leasehold land the extension of time for construction or the lessor’s NOC
- the application form signed by the owner and each professional, with their registration certificates
- the structural safety certificate, the certificate for supervision and debris removal, and an indemnity if there is a basement
- a soil test report for high-risk buildings
The bye-laws also make the architect inspect the site before submitting and confirm the drawings match what is there, including any existing construction (2.1.1(f)).
Checking who you hire
MCD publishes its lists of empanelled architects, engineers and supervisors, and of debarred professionals, on the same Citizen Corner page. Anyone calling themselves an architect must be on the Council of Architecture register, and our COA guide shows how to check.
Which master plan applies
The Master Plan for Delhi 2047 was notified on 20 Aug 2026 as an extensive modification of the 2021 plan, in force from publication. On 24 Oct 2026 MCD’s Ease of Doing Business page still linked the 2021 plan and a bye-law compendium updated to Feb 2020, with one later amendment of 24 Feb 2021. Ask your architect which norms the portal is checking against before the drawings are fixed. Farmhouse plots are a separate case, covered in our farmhouse rules page.
Questions
My plot is 180 sq m but faces a notified commercial road. Can my architect release the sanction?
No. A plot on a notified road goes to MCD’s Building Department whatever its size, as does any plot that needs an NOC. The route where your own professional releases the permit only covers plots with neither.
I’m adding a floor to an existing house. Which route applies?
The Building Department’s. MCD sends additions, alterations, revised plans and revalidations there for every plot size, so the professional-release route is only for fresh buildings.
Sources
- MCD Ease of Doing Business: Citizen Corner
- Unified Building Bye-Laws for Delhi 2016, compendium with amendments up to 12 Feb 2020 (DDA, hosted by MCD)
- MCD flowchart: building sanction for residential plots, low risk (105 to 500 sq m)
- MCD flowchart: building sanction for residential plots with NOCs or on notified roads
- DDA guidelines for decennial latent defect liability (lists Delhi’s sanctioning authorities)
- Gazette of India, S.O. 4597(E), 20 Aug 2026: Master Plan for Delhi 2047