Checked 24 Oct 2026
How a house plan gets approved in Gurugram
Explainers that still quote the Haryana Building Code as printed in 2017 give 15 days’ notice and 60 days for a decision. DTCP has amended it repeatedly since, most recently on 13 Aug 2026. For a plotted house, the current text lets you start sooner and makes the architect answerable for more.
Clause numbers below refer to the consolidated Haryana Building Code that the Department of Town and Country Planning (DTCP) publishes, which includes amendments up to 13 Aug 2026, unless we say otherwise.
Which office handles your plot
Three offices sanction most house plans in Gurugram, and which one you deal with depends on who developed the land. Each runs its own online system.
| Where the plot is | Who sanctions | Where your architect files |
|---|---|---|
| Municipal Corporation Gurugram area | MCG for most house plans, with the Directorate of Urban Local Bodies deciding change-of-land-use cases and high-risk buildings in the extended limits | obpas.ulbharyana.gov.in |
| A private colony developed under a DTCP licence, or a site with change of land use | DTCP, through the District Town Planner | ofa.tcpharyana.gov.in |
| A sector plot allotted by HSVP (formerly HUDA) | HSVP Estate Officer | obpas.hsvphry.org.in |
The split for municipal areas comes from the urban local bodies’ building plan page. DTCP has moved to a new online system and asks applicants to resubmit anything pending on the old one. HSVP’s portal description says a junior engineer scrutinises the drawings, then a sub-divisional engineer, and the Estate Officer gives the final approval.
The Gurugram Metropolitan Development Authority (GMDA) appears in the state’s orders on the city, for example as one of the bodies told to clear road encroachments in April 2026, but none of the house-plan systems above is run by it. If you are unsure which office applies, the allotment letter, sale deed or zoning plan for your plot names the body that issued it.
The risk category decides the route
Since the amendment of 22 Dec 2017, the code sorts buildings by risk (Code 5.1), and the category decides how the plan is approved. Under the wording substituted on 8 Dec 2025, a residential plotted building of any plot size, up to 16.5 m tall, is low risk. From 25 Jul 2024 until then, the low-risk limit for a plotted house was 16.5 m and a plot of up to 1,000 sq m. The 2017 original allowed self-certification only for houses up to 500 sq m.
The urban local bodies’ page, last updated 16 Jul 2025, still describes low risk as a building under 15 m on a plot under 1,000 sq m. That matches neither the current wording nor the 2024 one, so ask the municipal office which limit it applies.
A note added to Code 5.1 on 25 Jul 2024 reads: “The maximum permissible height of residential plots (outside core area), wherever occurring as 15 meters in the Code, shall be read as 16.5 meters.” It speaks of the maximum permissible height. The code does not say whether it also moves the other 15 m lines, such as sanction validity in Code 4.3 or supervision in Code 2.1(2), so ask the sanctioning office if your design falls between the two.
What self-certification means now
Code 2.2(1) has the owner apply on Form BRS-I, with the documents listed in Code 2.1, “for intimation”. It then says: “The applicant may initiate construction immediately after submission of the application and documents.”
The plan is still checked after you start. DTCP’s workflow note for self-certified cases describes the portal checking the drawings automatically, then the district office verifying documents, with any observation sent within 15 days. The note is undated and refers to the older portal. Code 2.2(3) lets the authority check the plan and the building at any stage. If it finds violations, the owner removes them at their own cost, and the clause adds that “no plea of the owner shall be entertained for any default committed by the Architect engaged by him.” Self-certification then stands aborted for that building.
Deadlines in the code, then and now
| Step | Code as printed in 2017 | Code as amended to 13 Aug 2026 |
|---|---|---|
| Self-certified house | 15 days’ notice, build if no objection | Build on submission (Code 2.2) |
| Regular sanction | Order within 60 days, else deemed sanctioned | Order within 20 days, else deemed sanctioned if the plan conforms to the code and land use and all fees are paid (Code 4.5) |
| Sanction valid for | 2 years under 15 m, 5 years at 15 m and above | Same wording, with the 15 m line (Code 4.3) |
| Plinth (DPC) certificate | Deemed accepted after 15 days | Unchanged (Code 4.9) |
The occupation certificate is mid-change. The 8 Dec 2025 amendment hands the certificate for low-risk buildings to the owner’s architect (Form BRS-V), and for high-risk buildings to an empanelled third-party architect with at least five years’ experience, who has 18 days to decide. A DTCP memo of 26 Jun 2026 holds back parts of that amendment: the new occupation-certificate routes until a portal is ready and architects are empanelled, purchasable FAR until rates are fixed, and the removal of references to the National Building Code until replacements are notified. Until then “the earlier provisions of Haryana Building Code shall continue to be applicable”. It also says the amendment’s benefits will go only to sites whose zoning plan has been revised to the new controls. The memo does not mention the new risk categories in Code 5.1, which we read as in force. Nothing published since says the portal is live. Under the earlier text, the authority issues a self-certified occupation certificate within eight working days or it is deemed issued.
Two rules hold in both versions. A plotted house needs at least 25% of its permissible ground coverage built, including one habitable room, a kitchen and a toilet, before it can get an occupation certificate. And water, sewer and power connections are released only after the certificate is issued, so don’t plan a move-in date before it.
What the architect signs
Code 2.1(2) requires every applicant to appoint an architect or engineer to draw the plans and supervise construction. Either one may supervise a building up to 15 m including the stilt, and above that both must. The clause still says 15 m, not 16.5 m. Under Code 2.1(3), the owner, architect and engineer each digitally sign the application and the drawings and certificates that go with it.
The architect’s duties continue after approval. If they see a violation on site, they must tell the owner and the authority and stop supervising, and the authority then issues a stop-work notice to the owner. Code 4.10(6) makes owner and professionals jointly liable for a false report at completion, with a complaint for suspension of the architect’s registration and debarment from practice in Haryana. In Oct 2024 DTCP blacklisted 18 architects over occupation certificates issued for stilt-plus-four buildings during a ban, and offered compounding at ₹2 lakh per violation, The Tribune reported.
If the owner changes architect or engineer midway, the change must be reported within seven days, and work stays suspended until the new professional takes on full responsibility for the project (Code 2.2, note iv).
Only someone registered with the Council of Architecture may use the title “architect”, so check the COA register before you sign anyone on.
Documents you will need
Code 2.1(1) lists the base set, all filed online:
- ownership proof: sale deed, lease deed or the allotment authority’s possession letter
- a site plan and building plans, with drawings in .DWG format
- specifications on Form BR-II
- structural drawings and the certificate of conformity and structural safety
- a public health services plan, and fire safety and HVAC plans where they apply
- proof of registration on the dust control portal, for plots of 500 sq m and above in the NCR (added on 12 May 2025)
- the scrutiny fee of ₹10 per sq m of covered area
For plots in licensed colonies, DTCP’s checklist also asks for the zoning plan certified by the architect, a certificate from the colony’s developer that services are working, and an affidavit from owner and architect that they will not deviate from the zoning plan. The municipal checklist adds property tax receipts and any NOCs the site needs, such as fire, pollution control, airport height or highway access.
Floors and homes per plot
Since 13 Aug 2026, Code 6.3(3) sets one dwelling unit per floor and four per residential plot at most, “subject to fulfilment of terms and conditions, as specified by competent authority.” No such terms had been published by 24 Oct 2026.
A fourth floor over stilt parking is a separate question. New stilt-plus-four approvals in Gurugram are on hold under a High Court stay of 2 Apr 2026 and DTCP memos of 3 Apr and 21 Jul 2026. Our stilt-plus-four page tracks both.
Questions
My plot in a licensed colony is 600 sq m. Do I have to wait for approval before building?
Under the current code, no. At 600 sq m and up to 16.5 m, the house is low risk under both the 2024 limit of 1,000 sq m and the 8 Dec 2025 wording, so your architect files on DTCP’s portal and work can begin on submission. If the authority later finds something wrong, you pay to fix it.
The authority hasn’t replied in three weeks. Is my plan approved?
On the regular route, the 20-day limit has passed, so the plan counts as sanctioned if it meets the code and the land use and every fee is paid. Ask your architect to confirm all three before relying on it.
Can I change architects halfway through construction?
Yes, but the change has to be reported within seven days, and work stops until the new architect takes over. Since they take on responsibility for the whole project, expect them to inspect the site before signing.
Sources
- Haryana Building Code 2017, consolidated with amendments up to 13 Aug 2026 (DTCP)
- Haryana Building Code 2017, original text (Invest Haryana)
- Haryana Building Code 2017 with amendments up to 5 Aug 2024 (DTCP)
- DTCP memo of 26 Jun 2026 on implementing the 8 Dec 2025 amendment
- Directorate of Urban Local Bodies, Haryana: approval and revision of building plan
- DTCP: building plan approval process for self-certification cases
- DTCP memo of 16 Apr 2026 on road encroachments and stilt floors (addressed to GMDA and other agencies)
- DTCP home page (notice on the new online building plan system)
- DTCP amendment to the Haryana Building Code, 13 Aug 2026
- Council of Architecture (register of architects)
- HSVP: About OBPAS
- The Tribune, 21 Oct 2024: 18 blacklisted architects face ₹2 lakh penalty